| Ashland to Petersburg Trail Study | Infrastructure | Study | | |
| Audubon Drive Sidewalk | Infrastructure | Underway - Design | January 2021 | December 2021 |
| Azalea Avenue Pedestrian and Signal Improvement Project | Infrastructure | Underway - Construction | June 2021 | June 2022 |
| Bethlehem Road Improvements | Infrastructure | Underway - Design | December 2022 | November 2023 |
| Beulah Road Infill Sidewalk | Infrastructure | Completed | December 2020 | December 2020 |
| Bremo Road Improvements | Roads | Underway - Design | July 2022 | March 2023 |
| Chamberlayne Farms Sanitary Sewer Project | Infrastructure | Completed | December 2018 | February 2021 |
| Church Road Safety and Mobility Improvements | Infrastructure | Underway - Design | August 2021 | September 2021 |
| Church Road Sidewalk | Infrastructure | Underway - Design | September 2024 | March 2025 |
| Cobbs Creek Reservoir | Environmental | Underway - Construction | 20150701June 2017 | 20160301Dec 2022 |
| Cornerstone Community Farm | Community | Underway | August 2016 | July 2017 |
| Creighton Road Improvements - Sandy Lane to Laburnum Avenue | Roads | Underway - Right of Way Acquisition | 20210901December 2023 | 20230901December 2023 |
| Dabbs House Road Improvements | Roads | Underway | 20191101October 2020 | 20211101October 2022 |
| Dorey Park Shared Use Path, Phase II | Infrastructure | Underway | November 2020 | March 2021 |
| E. Laburnum Avenue Sidewalk Improvements | Infrastructure | Underway - Design | 20210501November 2021 | 20211101June 2022 |
| Engineered Wood Way Phase II | Roads | Underway - Design | December 2020 | December 2021 |
| Fairfield Area Library | Community | Underway | 20180601June 2018 | 20191001October 2019 |
| Fall Line Trail | Infrastructure | Study | | |
| Firehouse 19 | Community | Completed | 12/5/2016 | 2/28/2018 |
| Firehouse 20 | Community | Underway | 20201201December 2020 | 20220531Spring 2022 |
| Gaskins Road and Quioccasin Road Intersection Improvements | Infrastructure | Underway - Design | On Hold | On Hold |
| Gaskins Road Sidewalk | Infrastructure | Underway | May 2021 | November 2021 |
| Gay Avenue Sidewalk Improvements | Infrastructure | Underway - Right of Way Acquisition | 20201101August 2021 | 20210501February 2022 |
| Glen Allen Small Area Study | Study | Study | | |
| Glover Park | Community | In Progress | 20190701July 2019 | 20180520 |
| Greenwood Road Bridge Repair | Infrastructure | Underway | March 2019 | January 2023 |
| Horsepen Road / Glenside Drive Safety Improvements Study | Study | Study | NA | NA |
| Hungary Road Sidewalk | Infrastructure | Underway - Design | 20230101January 2023 | 20240101January 2024 |
| Hunton Park Boulevard Sidewalk | Infrastructure | Underway - Design | 20200101August 2021 | 20210801December 2021 |
| John Rolfe Parkway Sidewalk | Infrastructure | Underway - Design | July 2021 | July 2022 |
| Lakeside Avenue Bridge Replacement | Infrastructure | Underway | June 2023 | June 2025 |
| Lakeside Community Trail | Infrastructure | Study | | |
| Meredith Branch Sanitary Sewer Project | Infrastructure | Completed | April 2018 | June 2021 |
| MHDS East Clinic | Community | Completed | 20180601June 2018 | 20190628June 2019 |
| Montrose Terrace Area Water & Sewer Rehabilitation | Infrastructure | Underway - Construction | February 2021 | April 2022 |
| N. Parham Road Sidewalk and Traffic Signal Improvement | Infrastructure | Underway - Design | | |
| N. Parham Road Sidewalk Improvements, Phase I | Infrastructure | Underway - Design | 20191101April 2021 | 20200101July 2021 |
| Nuckols Road and Pouncey Tract Road Sidewalk | Infrastructure | Underway | 20200316March 16, 2020 | 20200801August 2020 |
| Nuckols Road Trail | Infrastructure | Study | | |
| Nuckols Road Turn Lane, Phase II | Infrastructure | Underway - Design | On Hold | On Hold |
| Oakleys Lane Improvement Project | Roads | In Progress | 20201101July 2021 | 20211201October 2022 |
| Parham Road Bridge Repair | Infrastructure | Underway | March 2021 | July 2022 |
| Parham Road Pedestrian and Transit Stop Improvements | Infrastructure | Underway - Design | September 2022 | January 2023 |
| Public Design Charrette | Study | Study | | |
| Pump Road Sidewalk Project | Infrastructure | Underway - Construction | 20200801May 2021 | 20201201December 2021 |
| Quioccasin Road and Parham Road Construction | Roads | Underway | 20170801August 2017 | 20180801August 2018 |
| Quioccasin Road Sidewalk Improvements | Infrastructure | Underway - Construction | 20200412April 2020 | 20200801July 2020 |
| Richmond-Henrico Turnpike Improvements | Infrastructure | Underway - Design | 20230401April 2023 | 20250401April 2025 |
| Richmond-Henrico Turnpike Sidewalk | Infrastructure | Underway - Design | September 2020 | October 2020 |
| Ridge Road Sidewalk | Infrastructure | Underway | May 2023** | May 2024** |
| Ridgefield Parkway Sidewalk | Infrastructure | Underway - Design | 20200801December 2020 | 20210201June 2021 |
| Ridgefield Parkway Sidewalk, Phase II | Infrastructure | Underway - Design | April 2021 | May 2021 |
| Rocky Branch Trunk Sewer & Abelia Road Sewer Replacement | Infrastructure | Underway - Construction | April 2021 | 20220831August 2022 |
| Route 5 Corridor/Marion Hill Study | Study | Completed | May 2017 | December 2018 |
| Sadler Road Improvements | Roads | Underway - Right of Way Acquisition | August 2023 | 20211001August 2025 |
| Short Pump Park Multi-use Trails | Infrastructure | Completed | May 2020 | July 2020 |
| Short Pump Town Center Virtual Design Charrette | Study | Study | | |
| Solar Photovoltaic System - Libbie Mill Library Roof | Environmental | Completed | 20190501May 2019 | 2019111November 2019 |
| Solar Photovoltaic System - MHDS East Center Roof | Environmental | Completed | 20190501May 2019 | 20191101November 2019 |
| Solar Photovoltaic System - Public Safety Building | Environmental | Completed | May 2020 | April 2021 |
| St. Claire Lane Sidewalk and Drainage Improvements | Infrastructure | Underway - Design | 20200101January 2020 | 20211001Fall 2021 |
| Taylor Farm Park | Community | Underway - Design | 20201001Feb 2021 | 20230531Summer 2023 |
| Three Chopt Road Improvement, Phase II | Roads | Underway - Right of Way Acquisition | August 2024 | November 2026 |
| Three Chopt Road Sidewalk | Infrastructure | Underway - Design | 20230201September 2022 | 20231201June 2023 |
| Tuckahoe Park Stream Restoration | Environmental | Underway - Design | 20201201March 2021 | 20211201July 2022 |
| Upham Brook Trunk Sewer | Infrastructure | In Progress | 20180801August 2018 | 20210201May 2021 |
| Virginia Center Commons Design Charrette | Study | Study | | |
| Westwood Small Area Study | Study | Completed | July 2018 | December 2018 |
| Whispering Pines/Commerce Acres Area Sanitary Sewer Rehabilitation | Infrastructure | Future Project | December 2019 | April 2021 |
| Wilkinson Road Culvert Replacement | Infrastructure | Underway - Design | 20211201December 2021 | 20231201June 2024 |
| Woodman Road Roundabout Project | Roads | Underway - Construction | Construction Start Date: March 17, 2020 | August 2021 |